Engineers and Contractors and Land Surveyors and Land Surveying and Las Vegas and Nevada and Utah and Arizona Civil engineers, construction, engineers, engineering, construction surveyors, land surveyors, global positioning surveyors, land surveyors commercial, landscape architects, las vegas, nevada, utah, arizona, kingman, cedar city, flagstaff Engineers and Contractors and Land Surveyors and Land Surveying and Las Vegas and Nevada and Utah and Arizona Engineers and Contractors and Land Surveyors and Land Surveying and Las Vegas and Nevada and Utah and Arizona Civil engineers, construction, engineers, engineering, construction surveyors, land surveyors, global positioning surveyors, land surveyors commercial, landscape architects, las vegas, nevada, utah, arizona, kingman, cedar city, flagstaff "> ProjectProfile

®
Project: Centennial Project
Location: Clark County, NV 
Completion: Summer 2007
Estimated Construction Cost: $300 Million


Two 500kv transmission lines with a construction cost of $300 million dollars.  Aerial control, centerline design topographic work, construction staking of 370 lattice towers, boundary retracement from BLM/USGLO plats and field notes to determine route alignment and easements for 80 miles of corridor.





Project: Nevada Solar One
Location: Boulder City, NV 
Completion: June 2007
Estimated Construction Cost: $266 Million

The 64MW Nevada Solar One concentrated solar power plant went online in the USA June 2007. With 400 acres of solar concentrators, Nevada Solar One has become the third biggest solar thermal power plant in the world.





Project: Flamingo Underground Transmission 
Location: Las Vegas, NV 
Completion: Summer 2010
Estimated Construction Cost: $70 Million

The project consisted of one (1) mile of two (2) double circuit duct banks, eight (8) transmission vaults, 12 each open air and GIS terminations and 36 splices all to be completed under a tight performance schedule.  The Sinatra project embodied all of Wilson’s underground transmission capabilities in that it combined not only cable installation and civil construction but splicing of open air terminations on steel poles as well as GIS terminations in a substation.  







Project: Searchlight Solar (Boundary & Topo Survey)
Location: Searchlight, NV 
Completion: December 2009
Estimated Construction Cost: 

20-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Searchlight, Nevada, 55 miles south of Las Vegas. Provided boundary and topographical survey for 212 acre property in Searchlight, NV. The parcel consisted of 14 mining claims. 







Project: Piute Solar (Boundary & Topo Survey)
Location: Lancaster, CA 
Completion: February 2011
Estimated Construction Cost: 

40-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Lancaster, CA Provided boundary and topographical survey for 320 acre property.




Project: Utica Solar (Boundary & Topo Survey)
Location: Near Fresno, CA 
Completion: June 2011
Estimated Construction Cost: 

40-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Lancaster, CA Provided boundary and topographical survey for 281 acre property.




Project: Favorito Solar (Boundary & Topo Survey)
Location: Mojave, CA 
Completion: June 2011
Estimated Construction Cost: 

40-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Mojave, CA Provided boundary and topographical survey for 277 acre property.




Project: Blackwell Solar (Boundary & Topo Survey)
Location: Mojave, CA 
Completion: June 2011
Estimated Construction Cost: 

50-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Mojave, CA Provided boundary and topographical survey for 400 acre property.




Project: Cordelia Solar (Boundary & Topo Survey)
Location: Bakersfield, CA 
Completion: June 2011
Estimated Construction Cost: 

80-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Bakerfield, CA Provided boundary and topographical survey for 595 acre property.




Project: Clearview Solar (Boundary & Topo Survey)
Location: Mojave, CA 
Completion: June 2011
Estimated Construction Cost: 

80-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Mojave, CA Provided boundary and topographical survey for 654 acre property.




Project: Century Solar (Boundary & Topo Survey)
Location: Landcaster, CA 
Completion: June 2011
Estimated Construction Cost: 

40-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Landcaster CA Provided boundary and topographical survey for 298 acre property.




Project: Tonopah Solar (Boundary & Topo Survey)
Location: Buckeye, AZ 
Completion: September 2011
Estimated Construction Cost: 

60-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Buckeye,  AZ Provided boundary and topographical survey for 480 acre property.




Project: Chino Vallley Solar (Boundary & Topo Survey)
Location: Prescott, AZ 
Completion: September 2011
Estimated Construction Cost: 

80-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Prescott,  AZ Provided boundary and topographical survey for 640 acre property.




Project: Cielito I-II Solar (Boundary & Topo Survey)
Location: Calexico, CA 
Completion: August 2011
Estimated Construction Cost: 

60-megawatt (MW) DC solar photovoltaic (PV) power plant that will be constructed near Calexico, CA  Provided boundary and topographical survey for 320 acre property.
Energy Projects
Always do right! This will gratify some people & astonish the rest.
1091 S. Cimarron Road Suite A1 Las Vegas, Nevada 89145  (o) 888.594.3257 (f) 702.933.9030
Copyright © 2013 Diamondback Land Surveying,LLC